Griesbach Stage 15


Project Name: Griesbach Stage 15

Contract Value: $ 1,462,500

Project Location: 108 Street & 146 Avenue, Griesbach Neighbourhood, Edmonton, AB

Project Description: Installed 675m of 675Ø, 750Ø & 900Ø Concrete Storm Sewer, 34 Vm of 1500Ø and 1800Ø Manholes, 93m of Storm Pipe removal, and 1 SWMF Control Structure c/w RTC Controls. GS Holdings was subcontracted MCL Group for this project.

Owner: Canada Lands Company

Consulting Engineer: AECOM Canada

Project Manager: Ryan Thompson, GS Construction